
Evaluation of Danish Uganda Country Programme, 1987-2005
1. Introduction
A Uganda Joint Assistance Strategy (UJAS) between key donors and the Ugandan Government is currently being developed. Denmark is considering these efforts in view to participate at a later stage. A joint evaluation of such a strategy will thus become relevant in the longer-term. However, the current evaluation of the Danish Uganda Country Programme is to be undertaken now, keeping the UJAS in perspective.
Danish bilateral development assistance to Uganda resumed in 1987 after the National Resistance Movement took over power. Uganda was among the first Danish 12 programme cooperation countries identified in 1989, and in 1990 a Danish Embassy was established in Kampala. The Danish assistance (including NGO-support and technical assistance) has grown substantially from a modest contribution of DKK 34 million during the first year reaching a peak in 2001 of DKK 472 million. Since then it has come down to approx. DKK 350 million in 2002 and 2003, and a little higher for 2004. By the beginning of the 1990s Uganda was the second largest receiver of Danish bilateral assistance. The total Danish funded assistance during 1987-2003 has been nearly DKK 5 billion (DKK 4,909 million or USD 700 million).
The Ugandan policies on poverty eradication has been seen by donors as a good example of country-led development – and has been a very good basis for the joint donor/ Ugandan principles of alignment. Many donors have contributed to Uganda’s own development efforts. The Danish development assistance has been a relatively stable part of the international development assistance to Uganda. From an initial level of 4-5 percent of all multilateral and bilateral aid, it reached nearly 10 percent in 2001. It is now again at the level of 5-6 percent of all aid. The total aid Uganda during 1987-2003 is estimated at the level of USD 1 billion equivalent to about DKK 70 billion. The Danish aid contribution thus is at the level of 7 percent of all aid to Uganda during the last 15 years.
The achievements of Uganda’s national political, social and economic development since 1986 have been remarkable, and are well documented:
Many challenges still need to be addressed:
The Ugandan-Danish co-operation has followed the international changes in aid approaches. The evaluation will assess achievements in the context of these changing approaches. Three phases can be distinguished:
Initially, the Danish support was composed of a multitude of separate projects within many sectors (support to the construction of Entebbe airport, construction and rehabilitation of grain silos, district development, and core support to the establishment of the Ministry of Gender demonstrate some of the diversity). But from 1996 the Danish-Uganda co-operation was based on a five-year strategy focussing on support to four sectors: agriculture, health, water and sanitation, and roads. In addition, private sector development, good governance, decentralisation and human rights were supported. A new strategy for 2004-08 was approved in 2003 by the Board of Danida, sustaining the chosen sector programme support, but linking the Danish assistance much closer to Uganda’s poverty reduction strategy, and introducing budget support (from 2006 and onwards).
The sector support programmes have been regularly reviewed, and Danida’s Quality Assurance Unit undertook a Performance Review of the Uganda programme for the first time in May 2003. The Performance Review recommended that an evaluation of the country programme was to be undertaken within a 2-3 year framework. A recent Performance Review was undertaken in June 2005. Although some sector and thematic evaluations of the long-term Danish development cooperation with Uganda has been undertaken, an evaluation of the substantial country programme in its totality has so far not been carried out.70
The Terms of Reference includes the following chapters: Ch. 2 includes the evaluation purpose. Ch. 3 outlines the main users of the evaluation. Ch 4 presents the evaluation approach, and Ch. 5 the evaluation questions. Ch. 6 includes the timetable and Chapter 7 the composition of the evaluation team. Ch. 8 has a description of how the evaluation will be managed, and finally Ch. 9 lists the expected evaluation outputs. There are two annexes to the Terms of Reference: Annex I is the Evaluation Matrix and Annex II the List of references.
2. Purpose of the Evaluation
2.1 Main evaluation objective71
The main purpose is to evaluate achievements against the overall development objective of poverty reduction in Uganda (as formulated in the Uganda PEAP of 1997 and 2004, and in the Danish Strategy ’Partnership 2000’). Still, the efforts and achievements will also be assessed against the contemporary context and standards prevailing at the time, when decisions were made. The evaluation will provide answers to the two overall evaluation questions concerning accountability and learning (see Danida Evaluation Guidelines).
2.2 Specific evaluation objectives
Specifically, the evaluation will answer if – and to which degree – Danish assistance to Uganda
Danish assistance72 will be evaluated in light of Ugandan national policies, and in the context of activities of other donors. Achievements will, to the extent necessary, be assessed against contemporary goals and standards. Assessment of impact will generally be restricted to the overall level of achievements of the combined support from donors to Uganda and the country’s own efforts.
Finally, the evaluation should review the progress against the specific indicators of the Danish 2004 country strategy – and make recommendations to possible adjustments of the strategy.
3. Intended Users of the Evaluation
The main users as concerns the accountability aspects of the evaluation are: the Prime Ministers Office, the Board of Danida and Danish and Ugandan parliamentarians. Concerning the learning aspects, users are primarily: relevant Ugandan authorities, Royal Danish Embassy, Kampala, and the country desk in Copenhagen. Overall, the public and civil society in Denmark and Uganda will be target groups of the evaluation.
4. Approach and Methodology
The evaluation must be carried out in accordance with the Danida “Evaluation Guidelines” (February 1999). There are three main components of the evaluation:
1. Danida has initiated a pre-study of all available documentation at Danida Copenhagen headquarters as well as at the Danish Embassy in Kampala, and the Uganda offices. The pre-study will identify key issues for the evaluation; establish a documentary-based overview of sectors, programmes and projects; identify significant changes over the period covered by the evaluation; establish an overview of the financial resources involved, the key resource persons involved; and of the agreements and policy dialogue between Denmark and Ugandan authorities. The pre-study will be conducted during October-November, 2005 and a final report will be submitted in January 2006. The pre-study result will provide an input to the main evaluation team. The pre-study consultants will be commissioned by a separate contract, and the consultants are to be available for briefing the evaluation consultant during the inception phase.
2. District poverty profiles will form an integral part of the evaluation. The Department of Agricultural Economics & Agribusiness, Makerere University is currently conducting such studies in co-operation with the Agriculture Sector Programme Support. The profiles will be ready in time for the actual evaluation exercise, and will be made available to the consultant. It will also be possible for the Consultant to define specific data requirements that they wish to extract from the database at Makerere.
3. The main evaluation will be carried out by external independent consultants cotracted through international tendering. The evaluation team will commence working in March 2006, and comprise desk and field studies, including a perception study based on interviews of Ugandan and other partners. Based on the input from the desk-study major key issues of debate, implementation modalities and observed results of the Danish assistance will be empirically founded and analysed through the perception study, which is to be carried out in the field by local consultants. The evaluator will propose a tentative methodology (including outline of questionnaire) of the perception study in the tender. The detailed methodology will be included in the Inception Report for final approval. Other elements of the main evaluation will be focus-group discussions, analysis of international trends, etc. The draft findings of the evaluation will be commented upon at workshops before being finalised.
The approach to the Uganda Country Programme Evaluation is inspired by the current debate among partners in the DAC Network on Development Evaluation. As noted by the DAC73, country programme evaluations are mainly concerned with the activities of individual donor agencies at project, sector and programme levels. Evaluations that are limited to the perspective of a single donor agency leave out important aspects of the interaction or incoherence of the contributions of different actors to the same process.
In general, programme objectives of donor agencies increasingly become identical with the goals that the governments of developing countries set for themselves. Furthermore, since the effectiveness of ODA depends on the efforts of a wide variety of actors, it is impossible, and often even irrelevant, to attribute specific outcomes to individual agencies. In order to establish to what extent ODA has contributed to the achievement of national development goals it is necessary to review the performance of all development actors – donors and partner country agencies – collectively.
5. Evaluation Questions
Inspired by the DAC, the evaluation questions are structured under four headings:
1. Context and framework conditions. Questions concern changes in the context and the framework conditions for the Danish financed efforts. And the developments achieved as a result of the combined Government and donor efforts. In particular the national poverty reduction plan, good governance, general reforms of public institutions, including decentralisation of the administration, the legal system and control bodies and reform of legislation will constitute a significant point of focus in the evaluation.
2. Combined donor efforts. Questions concern the effects of the combined donor effort. The focus will be on questions concerning partnership, alignment of support, harmonisation (e.g. comparison without the ODA-inputs), government revenues, remittances, and possible negative effect of ODA.
3. The contribution74 of Danish financed activities to Uganda’s development. Questions concern relevance and effectiveness of the assistance. The evaluation will document the processes and concrete results achieved through Danish efforts and assess the long-term effects of Danish support, not least as regards cross-cutting issues.
4. Implementation modalities and follow-up of Danish development assistance, Questions include exit strategies, and the efficiency and sustainability of the assistance. This includes the utilisation of parallel systems, adviser assistance, NGO assistance, accounting procedures, cost-efficiency and monitoring systems.
The focus – and hence the major part of resources – will be allocated to heading three and four, i.e. on the contribution of Danish financed activities to the effectiveness of the larger development co-operation effort and implementation modalities. Headings one and two will also be covered in the evaluation, but it will be limited and based almost exclusively on existing data and knowledge, and performed mainly as a desk study. A separate perception study of effects, issues and modalities of the Danish assistance will provide a major input to the headings three and four. The evaluation approach is outlined in the appended Evaluation Matrix for guidance. In the following, questions are further detailed under each of the four headings:
5.1. Context and framework conditions
The evaluation will (primarily as a desk study) at a macro provide an overview of the general development of Uganda since 1986 in broad terms as concerns economic, political, social and human as well as institutional aspects of development. The combined government and donor efforts have contributed to development under each of these aspects.
5.1.1. Overall economic and political development and context
Evaluation questions concerning economic aspects: What level of development has Uganda achieved? In absolute terms and relative to that of comparable countries? And compared to the post-war starting point in 1986?
To understand the conditions for providing development assistance, it will be important to describe the overall macro-economic development of the country – and compare it to similar countries that have received similar levels of development assistance. Also, we can assume a relationship between sound economic policies of governments/donors and positive economic results, and vice versa. Although, obviously combined government and donor efforts can be overtaken by international events (marginalisation of the African continent, international oil crisis, international financial crisis, etc.).
The section should be based on general indicators of economic development available from known sources (PEAP’s review, World Bank, African Development Bank, UNDP, Bureau of Statistics, Makerere University). And the figures could, if possible, be compared to 2-3 similar African and Asian countries. The figures should include i.a.:
Evaluation questions concerning political aspects: How does the foreign policy condition of the country affect political choices made and the development climate in general? Which economic policy has been followed by the Ugandan Government, 1986-2005? And which general sig-nificant reforms/policies have been implemented? In which way has the dialogue with donors developed during the period, and has the dialogue influenced overall political choices made?
Danish assistance to Uganda resumed in a post-conflict situation. Internal (especially in regions bordering the Sudan where LRA has been active throughout the period) as well as external (Uganda has throughout the period been a significant foreign policy actor in regional conflicts, e.g. in the Congo) peace and stability have been major issues throughout the period of Danish assistance. Hence, compared to other Danish Programme countries, political stability and security has played and continues to play a very important role on the agenda of the Ugandan nation.
It is important to go back to policy statements and plans that were launched and discussed at the beginning of the period and to recall what were the risks and opportunities that could be seen at that time. Reconstructions done without sufficient sensitivity to the political process and to the historical contexts in which goals and strategies were formulated may misjudge the original hopes and intentions of important political actors and hence distort the picture of what was really achieved. The evaluation should:
At the same time the political economy of Uganda plays a significant role for development potentials. The evaluation should describe national policies followed – and consider the Government/donor policy dialogue concerning these policies. Comparisons could be made, if possible, with 2-3 similar African and Asian countries. The evaluation should consider i.a.:
5.1.2. Overall human and social context and development
Evaluation question: Is overall economic development reflected in actual poverty reduction, human and social development in absolute and relative terms?
Human and social development – poverty reduction – is the ultimate goal of government efforts and international development assistance. Many countries experience impressive growth rates, increased investment, and greater participation in globalisation without this necessarily having any effect on the majority of the population. This is often the case for middle income countries, and not the case for countries like Uganda but should nevertheless be assessed.
The evaluation should provide answers to the general development concerning key Uganda indicators like:
5.1.3. Overall organisational capacity context and development
Evaluation question: How has the capacity of organisations and authorities developed during the period of investigation, how has service delivery developed and is the institutional context in general facilitative for development?
The organisational capacity context in Uganda provides an important framework for the provision of international development assistance. Hence, it is important to describe the context – and assess organisational development during the period under investigation, including both public (national and local authorities) and private organisations. Changes in the organisations’ outputs, i.e. their service delivery and products, should be indicators of development in capacity of the organisations.
Specific data sources of this aspect would be service delivery tracking studies, reports from the local governments, reviews of individual organisations and institutions, client’s surveys, etc. If possible, studies of the development of employment conditions and salaries of public and private employees should be included.
5.2. Contribution of the combined donor efforts
Evaluation questions: How did the international donor community as a whole contribute to Uganda’s development, to which degree was the support aligned with the national strategies and delivered in partnership with the Government and other partners, to which degree were the donors harmonising their support, and how can the dialogue between the international community and the Government be described?
The evaluation will at a general level assess how the combined donor efforts have contributed to the development of Uganda since 1986 as concerns economic, political, social and human as well as organisational development aspects. Under the four aspects, the combined donor efforts will be described. At this level, the evaluation will for instance describe donors’ share of the combined development and recurrent budget on a sector basis. At this level, the evaluation should also consider
The evaluation should consider the Government – donor policy dialogue, and the strategic choices taken by donors in selecting and supporting the various sectors, as well as how the organisational and capacity development of specific organisations has been supported. Key areas like e.g. the judiciary, land reform, decentralisation, Parliament, specific line ministries, and NGO could be assessed as examples at this level. Describing these aid forms, the proportion of external support in comparison with total budgets, their quantity and quality will provide a framework for comparison with Danish assistance.
5.3. Concrete results of Danish financed assistance76
Danish financed activities have been undertaken within the framework of the overall context and conditions. And Danish financed activities have constituted smaller or larger shares of the overall government and donor financed activities in the respective areas and sectors. Results of Danish financed activities cannot be assessed in isolation from overall efforts made and overall results achieved. The key question is: what has been the value-added to Uganda’s development by Danish assistance?77
As part of the evaluation, a perception study will be undertaken in which the “voice” of stakeholders (Ugandan and other donor representatives) will be heard. After identification of a number of important issues experienced during the delivery of the Danish assistance key stakeholders from political and administrative positions will be included as well as civil society representatives, academia, other donors and the general public will be questioned of their perception (which by definition is subjective, but none the less important) of the relevance, modalities and performance of the Danish financed assistance.
5.3.1. Contribution of Danish financed activities to overall macro-economic and political achievements
Evaluation questions concerning economic aspects: To which degree has Danish assistance contributed towards the overall macro-economic development of Uganda, 1986-2005? What was the content of the policy dialogue on economic policy – and which impact did it have on the policies followed by the Ugandan Government?
The evaluation will collect information on the following indicators:
Evaluation questions concerning political aspects: To which degree has Danish assistance and the policy dialogue with Ugandan authorities contributed towards the country’s political development?
The evaluation should:
5.3.2. Contribution of Danish financed activities to human and social development achievements
Evaluation questions: Did Danish assistance have any impact on key social and human development indicators? Did Danish assistance pay due consideration to cross-cutting issues? In which way does Danish assistance distinguish itself from that of other donors in terms of poverty orientation? In which way was Danish policy dialogue able to influence policies of the Government in the field of social development and poverty orientation?
The specific Danish contribution towards the overall development in key human, social and poverty indicators should be assessed. Hence, Danish involvement should be described and assessed, its significance (in volume, space – district distribution – and quality) compared to that of other donors should be assessed, and the policy dialogue with the Government described:
5.3.3. Contribution of Danish financed activities to organisational capacity achievements
Evaluation question: To which degree has Danish assistance contributed to organisational and institutional development in Uganda? And how has the policy dialogue between Danish and Ugandan authorities affected Government priorities and policies? What are the major similarities/differences between Danish assistance and the international assistance in general?
Provision of assistance towards organisational and institutional capacity development may be more difficult than physical. Building roads have significant impact on development potentials – and may be relatively easy compared to supporting the judiciary. Support to the judiciary may, however, be very difficult, but may – although only showing effect in the longer run – prove to be a highly effective way of supporting the overall development of a country. The key indicator of capacity development will be progress in outputs of the organisations (service delivery, policies or plans, production, etc.).
5.4. Implementation modalities
Evaluation question: What specific aid modalities characterise the Danish assistance that has affected the economic, political, social & human and institutional development? What effects can be observed from different modalities in terms of organisational capacity development and the sustainability of this development? Which perception of the implementation modalities of the Danish assistance is prevailing among Uganda Government, civil society and development partners?
The perception study will be a major source of data for the assessment of the implementation modalities of the Danish assistance. Prior to the fielding of the evaluation team, a pre-study will be conducted of the archives of Danish-funded projects and programmes should i.a. provide data and documentation on preparation, implementation, reviews and evaluation of completed (and current) projects and support programmes, and involved desk officers, advisers and counterparts. Time lines of major events and decisions (by Danish or Ugandan offices) should established, and key documents like appropriation, minutes of annual consultations, programme document, appraisal, review and evaluation should be availed in electronic format. Based on the pre-study identification of key issues, the perception study will assess how Danish assistance has been perceived among the Uganda and other development partners.
As Danish assistance has had particular focus on for instance capacity development of the judiciary, the Parliament and decentralisation and strengthening of local government organisational capacity within these sectors are of particular interest. However, capacity development within other key areas, not receiving substantial support from Denmark like the education sector, could be included for purpose of comparison.
It is anticipated that the evaluation will be completed by November 2006, as indicated below. The tentative time schedule of the evaluation is as follows:
| Pre-study of archives | Sept 05-Jan 06 | |
| District Poverty profiles – main results (Makerere) | Nov 05-Jan 06 | |
| Tendering and contracting of evaluation | September 05-February 06 | |
| Mobilisation of Consultant | March 06 | |
| Phase 1: | Briefing, desk-studies, drafting Inception Report incl. work plan for field-work |
April 06 |
| Workshop in Kampala on Inception Report | 8 May 06 | |
| Phase 2: | Field-studies, perception study | May-June 06 |
| Phase 3 | Analysis, drafting of Draft Report | July-August 06 |
| Phase 4: | Discussion of draft report, Workshop in Kampala on Draft Report |
September-October 06 20 September 06 |
| Phase 5: | Final report, | 10 October 06 |
| Workshop in Copenhagen on Final Report | 15 November 06 | |
7. Composition of evaluation team
An evaluation consultant team, selected through global tendering, will carry out the evaluation. The organisation of the team’s work is the responsibility of the consultant and should be specified and explained clearly in the proposal. The evaluation team should possess the following qualifications:
General qualifications:
Specific qualifications for all team members:
Specific qualifications to be covered by at least one of the team members:
Experience from the Country/Region:
The evaluation team should be composed of international as well as local Ugandan (or regional) consultants. International consultants are defined as persons with an international background, e.g. a degree from an internationally recognised university and with a major part of professional experience from assignments within several developing countries as well as developed countries and working for recognised international consultants.
The individual team members should not have been involved in preparation, implementation or review of Danish funded programmes in Uganda, apart from minor assignments of a total duration of less than six person-months over the evaluation period.
8. Input
While the evaluators will have significant latitude in the design and organisation of their work, it is estimated that phase one will require four person-months’ work, phase two eight person months’ work, phase three six person-months’ work, and phases four and five two person months’ work. In addition, funds will be allocated to cover the reimbursable costs of logistics. A total input of 12 PM of international consultants and 8 PM of local Ugandan/regional is foreseen.
The consultant will propose the detailed methodology of the evaluation, including the specific methodology of the perception study, taking as point of departure the stipulated approach (as outlined in section four), and the Evaluation Matrix (Annex 1).
9. Evaluation principles, management and support
The basic DAC-evaluation principles of independence of those responsible for the design and implementation of the development intervention, and of utilisation of evaluators external to the donor and implementing organisations will be applied.
Responsibility for the content and presentation of the findings and recommendations of the evaluation rests with the evaluation team. The views and opinions expressed in the report will not necessarily correspond to the views of the Danish Government, the Uganda Government, or the implementing organisations. The report of the evaluation will be available to all relevant stakeholders and submitted to the Board of Danida, and to the Office of the Prime Minister.
Three sets of roles are contained in the evaluation process: the Evaluation Management, the Evaluation Team (Consultant), and the Evaluation Reference Groups:
Role of the Evaluation Management:
The Danish Uganda Programme Evaluation will be undertaken as a joint collaborative exercise of Danida’s Evaluation Department (EVAL) and Uganda’s Office of the Prime Minister (OPM), the latter being responsible for coordination and the strategy for monitoring and evaluation in Uganda. EVAL and OPM will each designate an officer and an alternate officer responsible for the evaluation. Together, the designated officers will form the Management of the evaluation.
Danida’s Evaluation Department will take a lead role as regards funding, contracting and implementation management. At the same time, participation in the evaluation will enhance the evaluation capacity of OPM, and the experience could be useful for future country programme assessment, in particular for future evaluation of joint strategies (UJAS). The OPM-officer will participate in the tender committee’s work.
The Evaluation Management will:
Role of the Evaluation Team (Consultant):
The evaluation is carried out through a contract with a consulting company/research institution by a team composed of external international and Ugandan consultants lead by an Evaluation Team leader. The team will:
Role of the Evaluation Reference Groups:
Two Reference Groups, one in Uganda and one in Denmark, composed of individual resource persons, researchers, and representatives of relevant offices, will be established. Representatives of other development partners may join the reference groups as observers. OPM will chair the Uganda Reference Group, while EVAL will chair the Danish Reference Group. The Danish Embassy in Kampala, and the Ministry of Finance, Planning & Economic Development, representing the Danish and the Uganda Governments, respectively, is responsible for the implementation of the Danish assistance to Uganda. As such, they are key stakeholders to the evaluation process, and will be participating in the work of the reference groups, but will not be responsible for the evaluation process or the results.
The task of the members of the reference groups are:
10. Evaluation output
The main outputs from the evaluation will be:
11. Requirements for the Consultant’s Home Office Intervention
The Consultants home office shall provide the following, to be covered by the Consultant’s fees:
The Tenderer should select a QA Team, envisaged to consist of minimum two persons, to be responsible for Head Office QA. The members of the QA should not be directly involved in the implementation of the Component and their CV should be included in the Tender. The QA team should have the same competence and professional experience as the Evaluation Team.
All QA activities should be properly documented.
The Tenders shall comprise a detailed description of the proposed QA, in order to document that the Tenderer has fully internalised how to implement the QA and in order to enable a subsequent verification that the QA has actually been carried out as agreed.
12. Information and Data provided by the Client
Reference is made to: i) Practical Guide to Tendering and Award of Larger Contracts by Danida, January 2004, ii) Users’ Guide to Sample Standard Tender Document for Larger Consultancy Contracts, January 2004 (http://www.um.dk), and iii) Evaluation guidelines, Danida, February 1999, Revised 2001 (http://www.um.dk/danida/evalueringsrap-porter/eval-gui/index.asp) .
13. Alternative Tenders
Alternative tenders will not be permitted.
14. Agreement of Exclusivity
The Consultant is not allowed to impose agreement of exclusivity on national sub-consultants.
Uganda Country Programme Evaluation. Evaluation Matrix. (version 16 September 2005)
The Approach
The Country Programme will be evaluated in its larger context, i.e. the contribution of Danida financed activities to the effectiveness of the larger development co-operation effort. Including whether – and to which degree – Danida operates in a supportive manner vis-à-vis the overall national (alignment) and international (harmonisation) development efforts? And with which resulting contribution to the development results, specifically concerning poverty reduction?
The Purpose
The purpose of the country programme evaluation is to answer if- and to which degree Danida’s assistance to Uganda
Finally, the evaluation should review the progress against the specific indicators of the Danish 2004 country strategy – and make recommendations to possible adjustments to the strategy. Achievement of impact is only assessed in the context of the overall level of achievements of the combined support from donors to Uganda and the country’s own efforts.
| The four evaluation headings (focus/priority on headings three and four) | ||
| Heading 1 The context and framework conditions | ||
| Questions/issues | Indicators and data | Data collection process/ methods and sources |
| Aspect 1. Overall economic and political context/achievements | ||
| Economic | ||
|
|
Government, World Bank, African Development Bank, UNDP, Bureau of Statistics, Makerere University). The figures could be compared to 2-3 African/Asian countries |
| Political: | ||
|
|
Scrutiny of key policy documents, laws. Interviews with policy makers, law makers, key players on the donor scene. Comparisons may be made with 2-3 similar African and Asian countries
|
| Aspect 2. Overall human/social development context/achievement | ||
| Is overall economic development reflected in actual poverty reduction, human and social development in absolute and relative terms? |
|
|
| Aspect 3. Overall institutional context and achievements | ||
| Evaluation question: How has the capacity of organisations and authorities developed during the period of investigation, how has service delivery developed and is the institutional context in general facilitative for development? | Use tracking studies of service delivery of specific organisations Use reviews and reports of e.g. local governments’ performance |
Analyse the Government’s and other responsible managers’ strategic choices of organisational development, resource allocation, etc. e.g. within the judiciary, land reform, decentralisation, parliament, etc. |
| Heading 2. Combined donor efforts | ||
| Questions/issues | Data and indicators | Data collection process, methods and sources |
| Aspect 1. Overall economic and political context/achievements | ||
| Economic: | ||
| The evaluation will at a general macro level assess the development of Uganda since 1986 as concerns economic, political, social and human as well as institutional development aspects. The combined donor efforts have contributed to development under each of these aspects. The evaluation will consider: |
|
Describing these aid forms, their quantity and quality will provide a framework for comparison with Danida assistance, since Danida has provided only grants and untied aid. |
| Political: | ||
|
|
Dialogue, focus groups, interviews, seminars with key policy players nationally and internationally. |
| Aspect 2. Overall human/social development context/achievement | ||
|
|
Contributions of donors towards specific social sectors (health & education) and production sectors (agriculture, infrastructure). Poverty profiles. Perception study |
| Aspect 3. Overall institutional context and achievements | ||
| Evaluation question: Has the organisational capacity context developed during the period of investigation, how did the international donor community contribute to its development, how can the dialogue between the international community and the government on institutional development be described, and is the institutional context in general facilitative for development? |
|
Identify the key organisations or institutions (public & private) which have been supported by donors Consider under which modalities the donor support has been delivered OECD/DAC, World Bank, UN studies on capacity development. Donor/government SWOT workshop |
| Heading 3. Concrete results of Danish financed activities – PRIMARY EVALUATION FOCUS | ||
| Questions/issues | Indicators and data | Data collection process/methods and sources |
| Aspect 1. Macroeconomic and political development | ||
| Economic: | ||
| To which degree has Danish assistance contributed to the overall macro-economic development of Uganda, 1986-2005? What was the content of the policy dialogue on economic policy – and which impact did it have on the policies followed by the Ugandan Government? |
|
|
| Political: | ||
| To which degree has Danish assistance and the policy dialogue with Ugandan authorities contributed towards the country’s political development? |
|
|
| Aspect 2. Human/social development | ||
| Did Danish assistance have any impact on key social and human development indicators? Did Danish assistance pay due consideration to cross-cutting i ssues? In which way does Danish assistance distinguish itself from that of other don ors in terms of poverty orientation? In which way was Danish policy dialogue able to influence policies of the Government in the field of social development and poverty orientation? |
|
|
| Aspect 3. Organisational capacity development | ||
| To which degree has Danish assistance contributed to capacity development in general, and to specific organisations in Uganda? And how has the policy dialogue between Danida and Ugandan authorities affected Government priorities and policies? What are the major similarities/differences between Danish assistance and the international assistance in general? |
|
|
| Heading 4. Implementation modalities and follow-up | ||
| Questions/issues | Indicators and Data | Data collection process, methods and sources |
| What specific aid modalities characterise international and Danish assistance, respectively as it concerns assistance that has affected the economic, political, social & human and institutional development? What effects can be observed from different modalities in terms of organisational capacity development and the sustainability of this development? Which perception of the implementation modalities of the Danish assistance is prevailing among Uganda Government, civil society and development partners? |
Consider
|
|
70) Support from the Industrialization Fund for the Developing Countries was evaluated in 2004, Danish assistance to health in 2000, poverty reduction in 1996, etc. The extensive evaluation in 2000 of the Rakai District Development Programme provided valuable insights concerning the support at the decentralised levels. Joint evaluations of sectors, where Denmark has not targeted support, e.g. basic education, are also available for possible comparison and assessment of relevance.
71) The current Strategy for the Danish Development Co-operation with Uganda for 2004-2008 states that impact evaluation of the development assistance to Uganda will be based on the total results of activities supported by the Ugandan government and by developmental partners, and an overall evaluation of the Danish development programme in 2005 or 2006 is foreseen. Meanwhile, it should be stressed, also in line with articles 32 & 45 of the recent Paris Declaration on Aid Effectiveness of April 2005, that all efforts to ensure that common arrangements and harmonisation with the partner country to the maximum possible will be taken for this evaluation, in particular through a close collaboration with Uganda’s Office of the Prime Minister, the designated focal point for monitoring and evaluation.
72) The evaluation will comprise Danish bilateral assistance to Uganda, including NGO assistance and Private Sector Programme. Danish contributions to multilateral organisations and multilateral programmes supporting Uganda (e.g. EU and UNDP) are not included.
73) DAC Room Document 2, 9 November, Paris 2004. The Network suggests a hierarchy of evaluation of aid effectiveness:
74) In this part of the evaluation, distinction is made between contribution (results of Danish assistance that was achieved because of a combined effort by Danida, Government and/or other donors), and attribution (results achieved primarily as a direct result of Danish financed activities).
75) Note that Dnida has oly provided grants and untied aid.
76) Note the distinction between contribution and attribution mentioned in note 74.
77) As concerns assessment of impact this will normally be restricted to the first level, and to a lesser degree to the second level. Analysis of contra-factual outcomes (non-intended or non-planned, negative or positive) should, if possible, be most relevant at level three of the contribution of the individual donor.